Construction and real estate

“This one here” still makes sense when you read the minutes.

On site, decisions are made while people point at a drawing. Nominute lets the engineer circle the spot on the drawing with Apple Pencil while recording; each stroke is tied to what was being said, and becomes a line in the minutes with grid line, drawing number, owner and due date.

Illustrative scenario

The project management unit of a property developer: a two-tower, 25-storey residential complex in Ho Chi Minh City, in superstructure works. A weekly site meeting with the main contractor, the supervision consultant and subcontractors.

The organisation, people, figures and documents on this page are fictitious and show how the product is used. They are not Nominute customers or measured results.

Who meets, and how often

  • Site meeting

    Weekly

    Owner, main contractor, supervision consultant, subcontractors: progress, safety, issues. 10–15 people, usually around a set of drawings.

  • Owner–contractor meeting

    Monthly or after an incident

    Design changes, variations, payments; what is agreed must be recorded fully enough to rely on later.

  • Inspection and acceptance

    Per work item

    Acceptance of works and stages; minutes on the prescribed form signed by all parties, with a defects list.

  • Design coordination

    Every two weeks

    Architecture, structure, MEP; many points are about a single detail on a drawing.

How minutes get written today

Site meeting minutes are usually written by an engineer from the project management unit or the supervision consultant: notes by hand in the site office, typed up in the evening. The hard part is everything said while pointing at a drawing, because “this one” and “that beam” mean nothing when read back.

  1. 01Comments tied to a drawing lose their context: the minutes say “adjust beam level” without the grid line or the drawing.
  2. 02Actions for subcontractors have no clear owner or date, so next week's meeting asks the same questions.
  3. 03When a variation is disputed, the parties dig through old minutes and cannot find who agreed to what.
  4. 04Sites are noisy, notes are rushed, and the abbreviations make sense only to their writer.

A typical meeting with Nominute

Week 46 site meeting · 60 minutes · 12 people from 5 organisations · level 9 structural drawing

  1. 01Before

    Bring the drawing into the meeting

    The project engineer creates the meeting on an iPad in the Tower A2 project and opens the level 9 structural drawing for notes. The attending organisations carry over from last week.

    Features used:

    • Template per meeting type
    • Apple Pencil notes
  2. 02During

    Circle it while it is being said

    When the supervision consultant points out that the beam soffit at grid C-3 clashes with the main duct, the engineer circles it on the spot. The stroke is tied to that second of the recording; tapping it later replays the exchange.

    Features used:

    • iPad recording
    • Pencil strokes tied to time
    • Speaker separation
  3. 03After

    Issues become actions

    The draft records progress by work item, technical issues with grid line and drawing number, and each organisation's actions with an owner and due date. An action nobody took on is flagged; no owner is guessed.

    Features used:

    • Actions with owner and due date
    • Traceable sources
  4. 04Approval

    The parties review

    The draft goes to the main contractor and the consultant through a comment-enabled link. The project director approves; the minutes lock with a time stamp.

    Features used:

    • Comment-enabled links
    • Approval and time stamp
  5. 05Send and file

    Each contractor gets their own actions

    The minutes go to every organisation; each person sees their own actions first. PDF and Word copies go into the project file.

    Features used:

    • Per-person emails
    • PDF and Word export

The industry's minutes template

An administrator builds the template once, or uploads the Word file already in use. Every meeting of that type then produces the same document.

Site meeting minutes: Progress by work item, Technical issues, Health and safety, Actions, Requests to the owner. No. CT-A2/046/BB-GB.
Minutes template · Site meeting minutes

Default for

Weekly site meetings, on-site issue meetings

Document number

{project}/{seq}/BB-GB

Next number: CT-A2/047/BB-GB

Sections · 5

  1. IProgress by work item
  2. IITechnical issues
  3. IIIHealth and safety
  4. IVActions
  5. VRequests to the owner

Signature block

SUPERVISION CONSULTANT · MAIN CONTRACTOR · PMU

Checked by the template

  • Technical issues carry the grid line and drawing number.
  • Every action has an organisation, an owner and a date; a missing one is flagged.
  • Points made on the drawing link to the stroke and the moment.
  • Three-party signature block.

Preview · A4

ABC INVESTMENT JOINT STOCK COMPANY

ABC RESIDENCE PROJECT MANAGEMENT UNIT

No. CT-A2/046/BB-GB

SOCIALIST REPUBLIC OF VIETNAM

Independence – Freedom – Happiness

Ho Chi Minh City, 13 November 2026

MINUTES OF SITE MEETING

Week 46 · ABC Residence, Tower A2

Time and place:
08:00–09:00, 13 November 2026 · Site office
Chair · Secretary:
Mr Trương Văn Lực, Project Director · Ms Mạc Thu Trang, engineer
Attendance:
PMU, XYZ main contractor, DEF supervision consultant, MEP subcontractor, façade subcontractor (12 people)

I. Progress by work item

Level 8 slab concrete completed on 10 November. Level 9 slab pour planned for 20 November, 3 days behind programme.00:06:30

II. Technical issues

Beam soffit at grid C-3 (drawing KC-09-03) clashes with the main duct by about 150 mm.00:18:42

Service opening at grid A–B/1–2 has no reinforcement detail.00:24:10

III. Health and safety

Fall-protection netting on the east side of Tower A2 is torn; main contractor to replace on 13 November.00:31:05

IV. Actions

MEP subcontractor to submit a duct lowering proposal for grid C-3 by 16 November.00:20:15

Issue the reinforcement detail for opening A–B/1–2: owner not identified.00:25:02to check

V. Requests to the owner

Main contractor requests approval for overtime to recover the 3-day delay.00:44:20

These minutes are sent to all attending organisations; any objections to the PMU within 24 hours.

SUPERVISION CONSULTANT

(Signature and full name)

Đinh Công Hậu

MAIN CONTRACTOR

(Signature and full name)

Lâm Quốc Việt

PMU

(Signature and full name)

Trương Văn Lực

Minutes drafted with Claude

In the product

In the product

Notes on the drawing, tied to what was said

Every Apple Pencil stroke carries the moment it was drawn. Tap the circle at grid C-3 to hear the consultant explain why the beam clashes with the duct; the same timecode goes into the matching line of the minutes.

The level 9 structural plan on an iPad with three numbered Apple Pencil notes: a circle at beam C-3, a circle round opening A–B/1–2, an underline at the stair core. Each note has a timecode in the recording.

In the product

Each contractor's actions, with dates

After the meeting every action has an organisation, an owner, a due date and the passage where it was assigned. An action nobody took on is flagged for the chair to confirm. Each person receives an email with their own actions first.

Five actions from the week 46 site meeting, each with owner, due date and timecode; one flagged as unassigned. Below, the email to the MEP subcontractor with his action first.

Compliance and security

Legal notes here are for orientation and are not legal advice. Nominute is a drafting tool; responsibility for the content of the minutes stays with the signatories.

  • Acceptance minutes keep their prescribed form

    Minutes for acceptance of works, stages and completion are still made under the construction quality regulations and the contract, signed by all parties. Nominute records the inspection, the defects to remedy and each party's actions, ready to go into those minutes.

  • A record when variations are disputed

    Each item in the minutes links to the recording. When quantities or a design change are disputed, the parties can hear the moment it was agreed instead of relying on memory.

  • Many organisations, one set of minutes

    Contractor and consultant representatives read, comment and confirm through links without an account. Links expire; administrators see who has opened and who has confirmed.

  • Recording on site

    Tell attendees before recording; the app reminds you. Losing signal does not lose the recording: it stays on the device and uploads when the connection returns.

  • Data

    Data is stored in Singapore, encrypted at rest and never used to train models. Each project has its own access list.

Time estimate, with the arithmetic

This is a calculation from the assumptions stated below, not a result measured at any organisation. Replace them with your own numbers.

6 meetings a month: 4 site meetings and 2 on-site issue meetings

Today, per meeting

Type up handwritten notes, check against drawings90 min
List actions for each contractor30 min
Circulate, collect and apply comments30 min
Total150 min

With Nominute, per meeting

Read the draft, check technical issues against drawings30 min
Confirm owners for flagged actions10 min
Parties comment on a single copy10 min
Total50 min
Difference per meeting
150 − 50 = 100 min
Per month
6 meetings × 100 min = 600 min, about 10 hours

Assumptions

  • Each meeting lasts about 60 minutes with 10–15 people.
  • Today's times are assumptions for a project engineer, not measured on any particular project.
  • Preparing acceptance minutes on the prescribed form is not included.

Recommended plan

Business

3 seats × 200,000 ₫ = 600,000 ₫ per month, before VAT

Business includes templates in the developer's branding, the approval workflow, administration and the activity log. Each project uses its own template and number series.

Who holds a seat

The project director (approver) and two engineers who take minutes. The main contractor, consultants and subcontractors read and comment through links.

Other industries

All solutions

Questions

Sites are noisy. Does recording work?

Hold the meeting in the site office and place the iPad near the speakers. Anything not heard clearly is marked to check rather than guessed.

Do Apple Pencil notes reach the minutes?

Yes. Circles and handwriting are tied to the moment in the recording; their content goes into the technical issues section with grid line and drawing number, each line linked to the exchange.

Does it replace acceptance minutes?

No. Acceptance minutes keep their prescribed form and the parties' signatures. Nominute records the inspection and the defects to remedy, ready to fill in those minutes.

Do subcontractors need an account?

No. They receive an email with their actions and a link to read, comment on or confirm the minutes.

Are minutes saved to the project folder automatically?

Today the minutes export to PDF and Word for the project file. Automatic saving to Google Drive and OneDrive/SharePoint is in development.

Try it on a real meeting of your own.